Project Title

Design and construction supervision of drilling camp, pad 2 and materials laydown area in Kingfisher discovery area

Project Description

The project covered the drill camp and construction supervision of a materials laydown yard and Kingfisher 2 (Pad 2). The Materials laydown area is a 185m x 200m gravel base platform which houses several structures that includes a chemical shed, marine shed, administration office, guard houses, water tanks, chemical showers, fire hydrants and security lighting.

Services Rendered

Detailed design, project management, and construction supervision.

Highlights

  • Project Sum: US $ 340,318
  • Client: China National Offshore Oil Corporation (CNOOC)
  • Status: Completed 2015