Design Review and Construction Supervision of Musita –Lumino / Busia – Majanji Road (104km)

Project Description

Upgrading from gravel to Class II paved (bituminous) standard of Musita – Lumino(77km) and Busia – Majanji (27km) road and 22km of town roads to be paved. A review and update of the original design and contract documents was undertaken simultaneously with construction supervision. Detailed design of some additional works including, was also undertaken.

Services Rendered

Design Review and detailed design of additional works including town roads, project  management, quality assurance, quantity and cost control, measurement of works and preparation of payments certificates, progress monitoring and reporting and defects notification period services.

Highlights

  • Project Sum: US $ 3,770,946
  • Client: Uganda National Roads Authority (UNRA)
  • Status: 2015 – Ongoing